Construction of Access controlled Nagpur - Mumbai super communication Expressway (Maharashtra Samruddhi Mahamarg) in the state of Maharashtra on EPC Mode for Package 07, from Km 296+000 to Km 347+190 (section - Village Bandra to Village Sawargaon Mal) in District Buldhana.

Location : Buldhana Dist, Maharashtra.

Type of Contract : EPC.

Length : 51.19 km.

Date of Commencement : 13 Apr 2019.

Date of Completion : 10 Dec 2022.

Project Cost : 1906.99 Cr.

Commissioned Under : Maharashtra State Road Corporation Limited (MSRDC Ltd.).

(Balance Work) of Khed Ghat Realignment (Km. on 46.981-Km. 51.400) & Narayangaon Bypass (Km. 76.300-Km. 81.200) Total Length-9.31 Km on Khed-Sinnr section of NH - 60(old NH-50) in State of Maharashtra on EPC Mode.

Location : Khed ghat - Narayangaon , Maharashtra.

Type of Contract : EPC.

Length : 9.31 km.

Date of Commencement : 19 July 2019.

Date of Completion : 20 Nov 2021.

Project Cost : 72.89 Cr.

Commissioned Under : National Highways Authority of India (NHAI).

Package PN-25 : Improvement of roads connecting the tourist destination in Pune District (Panshet, Lonawala, Rajmachi, Torna, Sinhgad, Purandar) (i) Khanapur to Panshet Km 0+000 to Km 16+470, (ii) Donje Kundanpur Khed Shivapur Km 7+500 to km 18+865, (iii) Saswad to Kapurhol km 54+500 to km 74+490, (iv) Mahad Madheghat Cheladi road SH-106 Km 29+400 to km 30+725 and (v) SH-106 to Torna Fort road VR1 Km 0+000 to 2+110. (Project No. PN-25) for 2-lanning with Paved Shoulder road in the state of Maharashtra under MRIP on Hybrid Annuity Mode.

Location : Narayangaon , Maharashtra.

Type of Contract : HAM.

Length : 51.180 km.

Date of Commencement : 20 July 2018.

Date of Completion : 20 Nov 2021.

Project Cost : 175.69 Cr.

Commissioned Under : Public Works (North)Division,Pune.

Operation and Maintenance of Yashwantrao Chavan Expressway – MSRDC (Km.00/000 to 94/600) and Mumbai Pune section of NH-48 (Old NH-4) (Km 20/400 to 131/200).

Location : Pune - Mumbai Expressway , Maharashtra.

Type of Contract : EPC.

Length : 111.000 km.

Date of Commencement : 10 Aug 2019.

Date of Completion : 28 Feb 2020.

Project Cost : 26.08 Cr.

Commissioned Under : Maharashtra State Road Corporation Limited (MSRDC Ltd.).

PACKAGE NO – PN 52 Improvements to Malharpeth- Umbraj- Masur- Mayani - Diganchi -Mahud - Pandharpur Road S.H.143 (Km 55/000 to 107/000 Dist. Satara & Sangali & Km 107/000 to 153/420 Dist. Solapur) ( Part-II Diganchi to Pandharpur Km 107/000 to km 153/420) Proposed length km 107/000 to km 153/420.

Location : Diganchi Pandharpur , Maharashtra.

Type of Contract : HAM.

Length : 46.280 km.

Date of Commencement : 20 July 2018.

Date of Completion : 25 July 2021.

Project Cost : 155.08 Cr.

Commissioned Under : Public Works Division,Pandharpur.

Development of Existing road in town Khed ghat (Km. on 46.981-Km. 51.400) & Narayangaon Bypass (Km. 76.300-Km. 81.200) Total Length-9.31 Km where bypasses are provided /being provided, excluding rehabilitation of Bridges on NH-60 in State of Maharashtra on EPC Mode.

Location : Khed ghat - Narayangaon , Maharashtra.

Type of Contract : EPC.

Length : 9.31 km.

Date of Commencement : 31 Aug 2018.

Date of Completion : 31 Aug 2019.

Project Cost : 30.74 Cr.

Commissioned Under : National Highways Authority of India (NHAI).

(Balance Highway and Structures works) Pune - Satara Road project – Km 789.000 to Km 820.000 Design, engineering, construction, development, finance operation and maintenance of 6 laning of -Pune - Satara section of NH-4 from Km 789.000 to km 820.000 in the state of Maharashtra under NHDP Phase IV on build ,operation and transfer (BOT) basis.

Location : Pune - Satara , Maharashtra.

Type of Contract : EPC.

Length : 31.000 km.

Date of Commencement : 21 Apr 2017.

Date of Completion : 20 Apr 2018.

Project Cost : 58.35 Cr.

Commissioned Under : Pune Satara Toll Road.

6 Laning of Pune - Satara Road of NH-4 from Km 789.000 to Km 820.000

Location : Pune - Satara , Maharashtra.

Type of Contract : EPC.

Length : 31.000 km.

Date of Commencement : 16 Oct 2016.

Date of Completion : 31 Jan 2019.

Project Cost : 249.98 Cr.

Commissioned Under : National Highways Authority of India (NHAI).

Khed – Sinnar Road project – Km 42.000 to Km 177.000 Design, Engineering, Construction, Development, Finance operation and maintenance of 4 laning of Khed - Sinnar section from km 42+000 to Km 177.00 of NH-50 (TU Project) Package 1 (from Km 42.000 to Km 72.396) in the state of Maharashtra under NHDP Phase III on design, build, finance, operation and transfer (DBFTO) basis.

The project involves four-laning of the Khed–Sinnar section of NH-50, which is a part of Delhi-Mumbai Industrial Corridor (DMIC) and an important link between Pune and Nashik, two major cities of Maharashtra. The project bypasses crowded urban areas and realigns hilly sections of the road to.

Location : Pune–Ahmednagar–Nasik, Maharashtra.

Type of Contract : EPC.

Length : 30.396 km.

Date of Commencement : 12 Feb 2014.

Date of Completion : 30 Apr 2018.

Project Cost : 171.92 Cr.

Commissioned Under : National Highways Authority of India (NHAI).

Pune - Solapur Road 4 laning Road Project - IL&FS Engineering and Construction Co. Ltd (Km 150.000- 170.000) in the state of Maharashtra.

Location : Pune - Solapur , Maharashtra.

Type of Contract : EPC.

Length : 20.000 km.

Date of Commencement : 10 March 2012.

Date of Completion : 31 March 2015.

Project Cost : 151.45 Cr.

Commissioned Under : IL & FS.